Respuesta :
Answer and Explanation:
The computation is shown below:
But before that first determine the predetermined overhead cost which is
= Estimated total manufacturing cost ÷ estimated labor hours
= $359,640 ÷ $9,990
= $36 per hour
Now the total cost is
= Direct material + direct labor + manufacturing overhead
= $25,500 + 1,700 × $10 + $1,700 × $36
= $25,500 + $17,000 + $61,200
= $103,700
Now the bid price is
= Job cost - markup profit
= $103,700 - $103,700 × 31%
= $103,700 - $32,147
= $135,847
To calculate the total Job Cost, it is required to add direct Materials with direct Labor and applied overhead.
Computation total job cost
Although when before that first determine the predetermined overhead cost which is
Then = Estimated total manufacturing cost ÷ estimated labor hours
Then = $359,640 ÷ $9,990
After that = $36 per hour
Now the total cost is
- Then = Direct material + direct labor + manufacturing overhead
- Now, = $25,500 + 1,700 × $10 + $1,700 × $36
- After that = $25,500 + $17,000 + $61,200
- Then = $103,700
Now the bid price is
- Then = Job cost - markup profit
- Now = $103,700 - $103,700 × 31%
- Then = $103,700 - $32,147
- Then = $135,847
Find out more information about Total job cost here:
brainly.com/question/26415931