Answer:
Yes
Explanation:
In order for deciding whether the company should forward or not, we have to find out the net present value which is shown below:
Year Cash flows Discount factor Present value
0 -274000 1 -274000
1 68000 0.8696 59130.43
2 73000 0.7561 55198.49
3 76500 0.6575 50299.99
4 78000 0.5718 44596.75
5 82500 0.4972 41017.08
6 77000 0.4323 33289.22
Total present value 283531.97
Net present value 9531.97
Since the net present value comes in positive so the project should be accpeted