if 12 people can finish a job by 5 days how many days will be required finish the same job by 10 people

Respuesta :

ishashunnny
ishashunnny ishashunnny
  • 01-09-2020

Answer:

4

Step-by-step explanation:

12p=5d

1p=5/12

10p=4.1666

≈4 days

Answer Link

Otras preguntas

What can geographers learn from location, place, and region ?
What types of internal differences and divisions exist within your faith?
Under the constitution the principle of federalism is the reason that power and responsibility are
hich best corrects the run-on sentence? The Belt of Orion has three bright stars in a row it is visible in the Northern Hemisphere. A. The Belt of Orion ha
The word "Semite" refers to a large language/ethics grouping that includes which two Middle Eastern people among its members?
Its says use rounding or compatible numbers to estimate the sum and example 198 + 727 ans is 200+725=925 I still don't understand how to do it. Heres a problem
A van is carrying 486 pounds. There are 27 boxes in the van What is the average weight of each box in the van
Factoring Quadratic Equations 4x³ + 43x² + 30x
How did speculative investing weaken the stability of the stock market
what is a sentence for the south pole