Answer:
48 days
Step-by-step explanation:
Let us assume the following things
Work done by 1 man in 1 day is [tex]\frac{1}{x}[/tex]
Work done by 1 woman in 1 day is [tex]\frac{1}{y}[/tex]
It is mentioned that
six men + ten women finished in 8 days
So,
[tex]\frac{6}{x} + \frac{10}{y} = \frac{1}{8}[/tex] .............. (1)
And,
four men + six women finished in 12 days
[tex]\frac{4}{x} + \frac{6}{y} = \frac{1}{12}[/tex] ...............(2)
Now solve these two equations
And we assume [tex]\frac{1}{x}[/tex] be u and [tex]\frac{1}{y}[/tex] be v
So
Now the equation is
[tex]6u\ + 10v\ = \frac{1}{8} \\\\\4u\ + 6v\ = \frac{1}{12}[/tex]
So,
u = 1 ÷ 48 , v = 0
Therefore x = 48
So the time taken for finish the work is 48 days