Answer:
Total future value= $645.8
Explanation:
Giving the following information:
Year 0 1 2 3 4
CFs: $0 $75 $225 $0 $300
Interest rate= 6.5%
To calculate the future value, we need to use the following formula on each cash flow:
FV= PV*(1+i)^n
Cf1= 75*1.065^3= 90.60
Cf2= 225*1.065^2= 255.20
Cf3= 0
Cf4= 300
Total future value= $645.8