What happens to most projects' value under the CAPM if there is a sudden increase to its market-beta

Respuesta :

ewomazinoade ewomazinoade
  • 21-08-2020

Answer:

Its value increases

Explanation:

Here are the options to this question :

its value decreases

Its value increases

Its value stays the same

According to the CAPM ,

expected return of an asset = risk free rate + (beta x risk premium)

If the beta increases, the expected return of the asset increases and the value of the asset increases

Answer Link

Otras preguntas

The time from one economic peak to another economic peak (think roller coaster ride) is called the _____. economic cycle Gross Domestic Product net exports
What is 15/8-3/8 ? Express the answer in simplest form.
Giuliana has 22 quarters and dollar coins worth a total of $10.75
what types of organisms produce sexually
What are the four most common gases in dry air?
why were alien and sedition acts unfair to new immigrants?
which of the following best describes the british position toward native americans afyer theRevolutionary War?         A. The British offered to take the Native
A snail crawls 300 cm in 1 hour. Calculate the snail's speed in each of the following units. A) cm/h B) cm/min C) m/h
Riddle: How many seconds are there in one year?
Read the following passage about sea turtles. In this activity, you will identify TWO examples of each of the different kinds of sentences that we are learning