Answer:
It will take them 2 2/5 days working together
Step-by-step explanation:
To find the time worked
1/a + 1/b = 1/t
Where a and b are the times worked individually and t is the time worked together
1/4 + 1/6 = 1/t
Multiply each side by 12t to clear the fractions
12t( 1/4 + 1/6 = 1/t)
3t + 2t =12
Combine like terms
5t = 12
Divide by 5
t = 12/5
t = 2 2/5
It will take them 2 2/5 days working together