10. In earned value analysis (EVA), we found: SV = -$7,800 at certain point. If the project has a total budget = $65,000 and total duration of 25 days. The project is: a. On schedule b. Ahead of schedule by 0.33 day c. Ahead of schedule by 3 days d. Behind schedule by 0.33 day e. Behind schedule by 3 days

Respuesta :

jereme06 jereme06
  • 29-07-2020

Answer:

3.5

Explanation:

Answer Link

Otras preguntas

Lavina wants to buy a rocking chair for 160$ she'll pay 10% down and pay the rest in six monthly installments.what will the amount of each monthly payment?
which of the following can be used to induce abortion non surgically? A. Estrogen B. Progesterone C. Mifepristone D. Dextromethorphan
What's the average score in an SAT and ACT?
selective college require more what than a high school
2/4+ sqrt 6 - 2/4- sqrt 6
Thermal power plants heat __ to create steam A wood B water C plants D fossil fuel
How do I solve for the answers because I don't know how to
organs in the digestive system
Can someone help me solve A-D? I have answers in the back of the book, but I can't figure out how they (they being the author of the textbook) got their answer.
What can you learn from looking at a phenotypic distribution?
ACCESS MORE