Teller Co. is planning to sell 900 boxes of ceramic tile, with production estimated at 870 boxes during May. Each box of tile requires 44 pounds of clay mix and a quarter hour of direct labor. Clay mix costs $0.40 per pound and employees of the company are paid $12.00 per hour. Manufacturing overhead is applied at a rate of 110% of direct labor costs. Teller has 3,900 pounds of clay mix in beginning inventory and wants to have 4,500 pounds in ending inventory.

Required:
What is the total amount to be budgeted for manufacturing overhead for the month?

Respuesta :

Answer:

Budgeted overhead= $2,877.6

Explanation:

Giving the following information:

Direct labor required:

Production= 870 units

Direct labor hours= 870*0.25= 218 hours

Direct labor cost= $12 an hour

Manufacturing overhead is applied at a rate of 110% of direct labor costs.

To calculate the allocated overhead for the period, we need to use the following formula:

Allocated MOH= Estimated manufacturing overhead rate* Actual amount of allocation base

Direct labor cost= 218*12= $2,616

Allocated MOH= 1.1*2,616= $2,877.6