Answer and Explanation:
a. The computation of the activity rate is shown below:
(a) (b) (a ÷ b)
Activity Estimated Expected Activity rate
Cost Pool Overhead Cost Activity
Labor-related $52,000 8,000 $6.50
direct labor-hours
Machine-related $15,000 20,000 $0.75
machine-hours
Machine setups 42,000 1,000 setups $42
Production orders 18,000 500 orders $36
Product testing $48,000 2,000 tests $24
Packaging $75,000 5,000 packages $15
General factory 108,800 8,000 $13.60
direct labor-hours
Total $358,800
b. The company predetermined overhead rate is shown below:
= Total estimated overhead cost ÷ direct labor hours
= $358,800 ÷ 8,000 direct labor hours
= $44.85