A constraint in the model means:__________.
1. activity A should be finished within 2 weeks.
2. the total time taken by activity A cannot be more than 2 weeks.
3. activity A cannot be crashed by more than 2 weeks.
4. activity A must be finished in week 2 after the start of the activity.
5. none of the above.