Answer:
The answer is 15000 F
Explanation:
Solution
Given that:
Direct materials purchased = $673,000
Standard cost of materials purchased = $688,000
Actual production = 22,000 unit
Standard price times real amount of materials = $ 444,000
Now we find the direct materials cost variances.
Thus
Direct material price variance = (444000-673000)
= 229000 U
Then
Direct material efficiency variance = (688000-444000)
= 244000 F
Total cost variance = (688000-673000)
= 15000 F
Therefore the direct materials variances is 15000 F