Answer:
Direct labor time (efficiency) variance= $11,000 favorable
Explanation:
Giving the following information:
Denver Co. recently used 14,000 labor hours to produce 7,500 units. According to manufacturing specifications, each unit is anticipated to take two hours to complete. The standard labor cost per hour is $11.
To calculate the direct labor efficiency variance, we need to use the following formula:
Direct labor time (efficiency) variance= (Standard Quantity - Actual Quantity)*standard rate
Direct labor time (efficiency) variance= (2*7,500 - 14,000)*11
Direct labor time (efficiency) variance= $11,000 favorable