Answer:
Product K91B= $10,743.82
Explanation:
Giving the following information:
Activity Cost Pool Activity Rate
Setting up batches $ 59.71 per batch
Processing customer orders $ 73.05 per customer order
Assembling products $ 4.40 per assembly hour
Product K91B
Number of batches 92
Number of customer orders 42
Number of assembly hours 496
We were given the allocation rates, all we need to do is allocate based on actual allocation base:
Allocated MOH= Estimated manufacturing overhead rate* Actual amount of allocation base
Product K91B= 59.71*92 + 73.05*42 + 4.4*496
Product K91B= $10,743.82