Answer:
Site B should be chosen based on the IRR criterion
Explanation:
Please check the attached image for the complete question
The internal rate of return is the discount rate that equates the after tax cash flows from an investment to the amount invested.
When comparing projects, the project with the highest IRR should be chosen.
I hope my answer helps you