Select all the correct answers.
Hattie's construction company is working on a building project. She is writing a progress report on the project: Which two graphics are
appropriate for her to use in the report?

a diagram labeling the different sections of a construction site

a table listing estimated costs for each stage of construction

a photograph showing the team members involved in the project

a chart showing the time taken to complete all past building projects
a chart comparing planned work and work actually completed

Respuesta :

Answer:

a chart showing the time taken to complete all past building projects  a chart comparing planned work and work actually completed

Explanation:

She is writing a progress report so she will not need the different sections of the consturction site, because she doesn't need location and she doesn't need a phorograph of the members involved in the porject and the cost, she is writing a report on progress