Respuesta :
Answer:
A) $82,622
Explanation:
first we must determine the net cash flows for years 1-4:
net cash flows = [(total revenue - total costs) x (1 - tax rate)] + depreciation expense
- CF1 = [($234,135 - $125,565 - $66,750 - $3,300) x (1 - 40%)] + $3,300 = $26,412
- CF2 = [($226,460 - $119,444 - $68,950 - $4,500) x (1 - 40%)] + $4,500 = $24,640
- CF3 = [($255,132 - $133,665 - $69,690 - $1,500) x (1 - 40%)] + $1,500 = $31,666
- CF4 = [($272,318 - $138,923 - $68,900 - $700) x (1 - 40%)] + $700 = $38,977
now we can calculate the project's NPV:
NPV = -10,000 + 26,412/1.11 + 24,640/1.11² + 31,666/1.11³ + 38,977/1.11⁴ = -10,000 + 23,795 + 19,998 + 23,154 + 25,675 = $82,622
Answer:
A) $82,622
Explanation:
The project's net present value (NPV) would be when using accelerated depreciation :
- The net cash flows for years 1-4 :
Net Cash Flows = [(total revenue - total costs) x (1 - tax rate)] + depreciation expense
- Net Cash Flows 1 = [($234,135 - $125,565 - $66,750 - $3,300) x (1 - 40%)] + $3,300
- Net Cash Flows 1 = $26,412
- Net Cash Flows 2 = [($226,460 - $119,444 - $68,950 - $4,500) x (1 - 40%)] + $4,500
- Net Cash Flows 2 = $24,640
- Net Cash Flows 3 = [($255,132 - $133,665 - $69,690 - $1,500) x (1 - 40%)] + $1,500
- Net Cash Flows 3 = $31,666
- Net Cash Flows 4 = [($272,318 - $138,923 - $68,900 - $700) x (1 - 40%)] + $700
- Net Cash Flows 4 = $38,977
The project's NPV :
NPV =Net Cash Flows ( 1+ 2²+ 3³+4⁴ )
- NPV= ( -10,000) + 26,412/1.11 + 24,640/1.11² + 31,666/1.11³ + 38,977/1.11⁴
- NPV = (-10,000) + 23,795 + 19,998 + 23,154 + 25,675
- NPV= $82,622
Thus ,the correct Net Present value is $82,622.
Learn more :
https://brainly.com/question/23943305?referrer=searchResults