Answer:
$754.34 per unit
Explanation:
Expected production of product F0 = 920 units
Total Product Cost F0
Total Direct labor hours cost = 6624 hours * $23 / hr = $152,352
Direct material cost- = 147.90 * 920 units = $136,068
Total Overheads cost of F0 ;
DLHs - 391,680 * 6624 /15088 = 171,957
Setup - 49,830 * 800 / 1700 = 56,949
MHs - 290,700 * 4100 / 8400 = 141,889
Total Overhead cost of F0 = 370,795
Total Product F0 cost = Total direct labor cost + Total direct material cost + total Overhead cost
Total product cost for F0 = 152,352 + 136,068 + 370,795 = $659,215
Total per unit cost for product F0 = $659,215 / 920 units = $754.34 / unit