A project can be completed by 5 workers in 24 days. How many workers are needed to finish the project in 15 days? The time
to complete a project is inversely proportional to number of people who are doing the project.
a 10
c. 6
b. 12
d. 8

Respuesta :

Answer: 8

Step by step explanation: 5 times 24 equals 120, 120 divided by 15 equals 8 which is the answer!

Answer:

d.8

Step-by-step explanation: