In class Assignment Setup of Production FacilityJobs Description Duration/ Weeks Predecessors1 Design production tooling 4 - 2 Prepare manufacturing drawings 6 - 3 Prepare production facility 10 - 4 Procure tooling 12 1 5 Procure production parts 10 2 6 Kit parts 2 3,4,5 7 Install tools 4 3,4 8 Testing 2 6,7 1. Draw the network diagram2. What is the critical path