Explanation please.PW of Project A is - $5,000. PW of Project B is - $6,000. PW of Project C is - $7,000. These are independent service projects and are mutually exclusive. Which project(s) should be selected? Group of answer choices Project B and C Project A and B Project A Project A and C Project C Project A, B, and C Project B