Answer:
B) repair costs resulting from damage to the plant asset while it was being unpacked.
Explanation:
In terms of IAS 16, cost of a Property, Plant and Equipment Item include the Purchase cost and any other costs directly incurred in placing the asset in the location and condition intended for use by management.
All other costs above are costs directly incurred to place the Plant asset in location and condition intended for use by management except repair costs resulting from damage to the plant asset while it was being unpacked.