Respuesta :
Answer: $7800, difference of $440
Explanation:
Items shipped = 120,000
Variable overhead cost = $7360
direct labour hours monthly = 2300
company labor per hour per item = 0.02
Variable overhead rate per hour per direct labour = $3.25
Variable of overhead cost required to fill 120,000 orders
Orders shipped × labor per hr × variable overhead per hr.
= 120000 × 0.02 × $3.25
= $7800
Difference in variable over head
= $7800 - $7360
= $440
Answer:
The variable overhead cost that should be incurred to meet order demand for 120,000 items is $7800. The difference from the actual cost is $440.
Explanation:
Given information:
The number of shipped items is 120,000.
Direct labor cost is 2300.
The variable overhead cost is $7360.
Direct labor hours required is 0.02 per item.
The variable overhead rate is $3.25 per hour.
The formula to compute standard variable overhead cost that is required to fill an order of 120,000 items is as follows:
Initially, the total labor hours would be derived by multiplying the total number of shipped items with standard direct labor hours.
[tex]120,000*0.02\\= $2400[/tex]
Thus, the total labor hours is 2400.
Now, the total labor hour allowed would be multiplied with the standard variable overhead cost.
[tex]2400*3.25\\=$7800[/tex]
Thus, the total standard variable overhead cost is $7800.
The variance in overhead cost is derived by subtracting actual overhead cost from total standard variable overhead cost, which is:
[tex]7800-7360\\=440[/tex]
Hence, $7800 overhead cost would fulfill the demand for an order of 120,000 items. And, the variance difference between actual overhead cost and total variable overhead cost is $440.
For more information, refer to the link:
https://brainly.com/question/15574091?referrer=searchResults