Answer:
b) $920,000
Explanation:
Under Completed contract method,the revenue is recognized only when the contract is 100% complete.
As the contract is not completed in 2021 , the profit is recognized only in the year of completion
If in case question is asked about % of completion answer should be as fallows:
Total gross profit on the contract = total contract value – total estimated cost
= 24,000,000 -22,000,000
= 2,000,000
Total cost in 2021 = 10,120,000
Total % of completion in 2021 = total cost in 2021/ total cost of contract
= 10,120,000/22,000,000
= 46%
Gross profit in 2021 = total gross profit on contract x Total % of completion in 2015
= 2,000,000 x 46%
= $920,000