Answer:
$260 per day
Explanation:
Handfield Manufacturing Co.
Holding cost = 35% annually = 0.35
Standard Cost = $271,590
Number of Days in a Year = 365 days
Hence;
Daily Holding Cost = (Standard Cost x Holding Cost) / Number of Days in a Year
Daily Holding Cost = ($271,590 x 0.35) / 365
Daily Holding Cost = $260 per day
Extra Driver Cost = $180
Hence the benefit of subcontractor who will team with an effective delivery of 1 day can be calculated as follows;
Daily Holding Cost - Extra Driver Cost
= $260 - $180
= $80
Therefore, the use of subcontracting the team who will drive overnight is more economical, with a daily cost of $260 per day.