Since 100 shutters are scheduled to be finished in 3 weeks, you must order the 200 frames immediately so they arrive at the end of 2nd week or beginning of the 3rd week. This way, you can assemble the parts during the 3rd week and have them finished by the beginning of the 4th week when they must be delivered.
The other order, 150 shutters must be finished in 7 weeks, so you can order the 300 frames at the end of the fourth week. This way the frames will be received by the end of the 6th week and the parts assembled during the 7th week.
Lot-for-lot order quantities are carried out for every job order that required them.