Answer:
Part A)
Processing time for Each Batch = Setup time + Production time
Processing time for Each Batch = 20 + 2 × 10
Processing time for Each Batch = 40 minutes
Thus,
Capacity for one day = Total working Hour / processing time
Capacity for one day = 8 hours / 40 minutes
Capacity for one day = 12 batches
(6 batches of each donuts type, or 60 donuts of each type)
Part B)
Total production time for both donuts = (80 + 80) × 2
Total production time for both donuts = 320 minutes
Time for Total batch = 480 - 320
Time for Total batch = 160 minutes
Batch time available for each type = 160 / 2
Batch time available for each type = 80 minutes.
Number of batches = 80 minutes / 20 minutes
Number of batches = 4 batches
Thus,
Minimal batch size = 80 donuts / 4 batches
Minimal batch size = 20 donuts for each type of donuts in single batch.