If three workers are assigned to a task lasting four days, two workers are assigned a task lasting three days, and one worker is assigned to a task lasting three days. The tasks can be completed independently of each other. If you are to schedule with a resource-limit, what is the minimum resource limit for the project

Respuesta :

Three workers per day is minimum resource limit.

Explanation:

Every day he needs maximum of 3 workers, so this can be set of the minimum resource limit for the project.

Thus, the minimum resource limit for the project is -  Three workers per day

All asset make and change demands are assessed against each LimitRange object in the task. In the event that the asset abuses any of the listed requirements, at that point the asset is dismissed. In the event that the asset doesn't set an express worth, and on the off chance that the imperative backings a default esteem, at that point the default esteem is applied to as far as possible is an edge for an asset the executives and helps control asset use. A procedure for overseeing limits takes into consideration the reallocation of assets to various clients or activities as necessities change.

The minimum resource limit for the project would be:

- 3 workers every day.

  • In the given scenario, each day requires at least three workers to accomplish the required task.
  • The given descriptions suggest that a total of three workers are assigned, the first two for the initial three days and the latter for the last three days, and each one can finish it on themselves only.
  • This implies that the lowest limit of human resources for the project would be 3 workers irrespective of the challenges or problems that might occur.

Learn more about 'Resource Limit' here:

brainly.com/question/439768