Answer:
The correct answer is letter "B": Linear responsibility chart.
Explanation:
A Linear Responsibility Chart (LRC) is, just like its name indicates, a chart where all the participants of a project are in a hierarchical order so subordinates will know who to report and what the command structure of the group is. LRCs display the function of the main representatives of the plan to be carried out so they are helpful to create correct lines of communication and coordination during the development of the project.