Respuesta :
Answer:
The question is incomplete, this is the remaining part
c -> e -> g -> l \
A / \
\ B -> D -> F -> k -> n -> O -> P
\ H -> M /
(The capital letters are the darker boxes)
Answer is...
this represents the path of tasks that will take the longest to complete.
Explanation:
PERT can be described as a basic network technique that includes planning, monitoring and control of project. It can also be described as a technique that is used to manage uncertain activities of the project.
PERT is very important because it helps to calculate the free and total slack of a project.
In this case, the PERT formula, represents the path tasks that will take time in completion.
It should be noted that, PERT was first used in 1957 by Booz, Allen and Hamilton, as a method of planning and controlling the Polaris Missiles Programme .