Respuesta :
Answer:
this was a breach of the contract
Explanation:
In this case, there was a breach of contract on the part of STR. First, the project was behind the schedule and NTI did its part. Then, the STR employees damaged the work that NTI had done. In this right, NTI has the right to be compensated and paid for the work that was done. The onus falls upon the STR to pay the subcontracted NTI irrespective of whether the kitchen as accepted or not. This was because the renovation of the kitchen depended sorely on the responsibility of STR not NTI.
Answer:
this was a breach of the contract
Explanation:
In this case, there was a breach of contract on the part of STR. First, the project was behind the schedule and NTI did its part. Then, the STR employees damaged the work that NTI had done. In this right, NTI has the right to be compensated and paid for the work that was done. The onus falls upon the STR to pay the subcontracted NTI irrespective of whether the kitchen as accepted or not. This was because the renovation of the kitchen depended sorely on the responsibility of STR not NTI.