During which of the following Project Schedule Management processes does the team estimate the number of work periods that will be required to complete a schedule activity, usually expressed as workdays or workweeks? ​ a. Define activities b. Sequence activities c. Develop schedule d. Estimate activity durations

Respuesta :

Answer:

d. Estimate activity durations

Explanation:

Based on the scenario being described within the question it can be said that this is done during the management process known as Estimate activity duration. Like mentioned in the question this is the process of generating an estimate of the number of work time needed to complete specific individual activities with a given number of available resources.

Answer:

Option d. Estimate activity durations

Explanation:

Estimate Activity Durations can be define as the process of estimating the total amount of work that will be needed to finish an individual activities which is estimated with the resources that is available. One of the main benefit of this method is that it gives an estimated number of time every activity will take to so that activity will be completed, which is a major input into the Develop Schedule process. From the case in this question, we can see that the management did an estimate of periods needed for the to complete a schedule given to them, they did an estimate activity duration to be able to determine this.

Otras preguntas

ACCESS MORE
EDU ACCESS