Respuesta :
Answer:
physical flow schedule is express as
Explanation:
physical flow schedule is express as
Quantities Physical Units in Gallons Material Conversion
Units to be accounted
Work in process July 1 10,600
(Direct Material - 100%,
Conversion Cost -70%)
Started into production 87,800
(98,400 Units - 10600 Units)
Total units 98,400
Units accounted for
Transferred out 83,000 83,000 83,000
Work in process, July 31 15,400 15,400 10,780
(Direct Material - 100%,
Conversion Cost -90%)
Total units accounted for 98,400 98,400 93,780
and
Material Conversion
Units Both Started & 72,400 72,400
Completed During July
Units in Beginning WIP ×
Percentage to Complete
Material = 10,600 × 0% 0
Conversion = 10,600 × 30% 3180
Units in Ending WIP × Percentage Complete
Material = 15,400 × 100% 15400
Conversion - 15,400 × 90% 13860
Equivalent Unit Under FIFO Method 87,800 89,440
(= 72,400 + 15400 = 87,800
= 72,400 + 3180 + 13860 = 89,440)
and
Material
Units Both Started & Completed During July 72,400
Units in Beginning WIP ×
Percentage to Complete
Material = 10,600 × 40% 4240
Units in Ending WIP × Percentage Complete
Material = 15,400 × 60% 9240
Equivalent Unit Under FIFO Method 85,880
72,400 + 4240 + 9240 = 85,880