Answer:
$32
Explanation:
The incremental cost:
Direct materials +Direct labor +Variable manufacturing overhead
$12 + $8 + $12 = $32
The maximum price Olive Corp. should pay the outside supplier is $32.
Fixed manufacturing overhead was not included because it is not relevant to the decision.