Answer:
$105,000
Step-by-step explanation:
The computation of the total prevention cost appearing on the quality cost report is shown below:
Total prevention cost = Quality circles + Statistical process control activities
= $27,000 + $78,000
= $105,000
While determining the total prevention cost we simply added the two cost only i.e quality circles and the statistical process cost so that the correct amount could arrive