Respuesta :
Answer:
The budgeted Direct labor cost for August is $73920
Explanation:
The budgeted direct labor cost for August can be calculated by multiplying the labor rate per hour by the Labor hours worked in August.
As one unit consumes 0.4 Labor Hours. The labor hours worked in August are,
Labor hours- August = 0.4 * 8400 = 3360 Labor Hours
The Labor cost for August are budgeted to be,
Direct Labor Cost- August = 3360 * 22 = $73920
Answer:
August $73,920
Explanation:
JULY
Budgeted production units $8,200
Labor requirement per unit (hours) 0.40
Total labor hours needed($8,200×0.40) $3,280
Labour rate per hour($3,280×$22)
Labor dollars $72,160
AUGUST
Budgeted production units $8,400
Labor requirement per unit (hours) 0.40
Total labor hours needed($8,400×0.40) $3,360
Labour rate per hour($3,360×$22)
Labor dollars $73,920
Therefore the total cost of direct labor budgeted for the month of August is: $73,920