Explanation:
1. Calculation of labor spending variance for the month of march
Labor spending variance = (Actual rate x actual hours)- (Standard rate x Standard hours)
=(13 x 63000) - (12 x (26000 x 3))
=-1,38,600
Labor spending variance for the month of March is $138600
2.Calculation of variable manufacturing overhead planning cost
Variable manufacturing overhead planning cost= (Planning budget units x required hours x cost per hour)
=(21000 x 3 x7)
=441,000
Variable manufacturing overhead planning cost is $441,000
3. Calculation of Variable manufacturing overhead cost
Variable manufacturing overhead cost= (Actual units x required hours x cost per hour)
=(26600 x 3 x7)
=$558,600
Variable manufacturing overhead cost is $558,600
4. Calculation of Variable overhead rate variance
Variable overhead rate variance= Actual hours ( actual rate - standard rate)
=63000((510930/63000)-8)
=63000(8.11-8)
=63000(0.11)
=6930
Variable overhead rate variance is =6930