Respuesta :
Answer:
the latest an activity can be started and still finish the project on time, calculated by subtracting the activity's duration from its latest finish time
Explanation:
In project management, slack refers to the amount of time that a certain task can be delayed and not affect the completion time of the general project. Slack time can be considered "just in case" time, because even though delays should be minimized, rarely you can eliminate them completely, and slack time gives you a little extra room for managing projects.
Answer:
The correct answer is letter "B": the difference between an activities latest start time (LS) and earliest start time (ES).
Explanation:
Slack time refers to the interval time when activities can be completed before the time they are planned. It can be understood as the difference between the Latest Start (LS) time and the Earliest Start (ES) time for that task. Managers must be aware of the slack time of the operations of their companies because it allows them to identify which activities can be left aside to allocate all the sources available to critical tasks. Those critical activities must have a slack time of zero (0).