Respuesta :
Answer:
Sawing: $5.50
Polishing: $3.00
Explanation:
[tex]\frac{Cost\: Of \:Manufacturing \:Overhead}{Cost \:Driver}= Overhead \:Rate[/tex]
We have to solve usign the expected values as the predetermined rate is calcualted before the activities are done.
Sawing:
expected overhead 275,000
cost driver: machine hours
expected MH 50,000
overhead rate: 275,000 / 50,000 = 5.5
Polishing:
expected overhead 180,000
cost dirver labor hours
expected DL 60,000
overhead rate: 180,000 / 60,000 = 3.0
Answer:
Bid Price of the Project = $35 Per Square Meter.
Actual dimensions is 4 by 25 Square meter
Actual Revenue therefore = 4 x 25 x 35 = $3,500
Actual Costs = Sawing ($7.29 x 126 hrs) + Polishing ($16.50 x 130 hrs) = ($918.54 + $2,145) = $3,063.54
Profit = $3,500 minus $3,063.54 = $436.46
Yes, the company made a profit of $436.46
Explanation:
Compute the cost to be assigned to the Washington County job. The job had been bid to the customer at a sales price of $35 per square foot, and the final dimensions are 4' X 25'. Did the company make a profit on this job?
Sawing & Polishing department Actual Costs For the year:
Direct Labor $121,000 || $802,00
Direct Materials - $73,400 || $8,000
Factory Overhead - $129,000 || $188,000
Total Direct Costs = $323,400 || $998,000
Direct Labor Hours - 9,600 Hrs || 60,500 Hrs
Sawing machine hours - 44,500 Hrs || n/a
Actual Factory Overhead allocation =
$323,400 divided by 44,400 hrs = $7.29 Per Sawing Machine hour (Sawing Department)
$998,000 divided by 60,500 hrs = $16.50 Per direct Labour Hour (Polishing Department)
Sawing & Polishing department Budgeted Costs For the year:
Direct Labor $125,000 || $800,000
Direct Materials - $75,000 || $6,000
Factory Overhead - $275,000 || $180,000
Total Direct Costs = $475,000 || $986,000
Direct Labor Hours - 10,000 Hrs || 60,000 Hrs
Sawing machine hours - 50,000 Hrs || n/a
Budgeted Factory Overhead allocation =
$475,000 divided by 50,000 hrs = $9.50 Per Sawing Machine hour (Sawing Department)
$986,000 divided by 60,000 hrs = $16.43 Per Direct Labour hour (Polishing Department)
Sawing & Polishing department Washington County Courthouse project Costs:
Direct Labor $300 || $1,770
Direct Materials - $185 || $20
Factory Overhead - $0 || $0
Total Direct Costs = $485 || $1,790
Direct Labor Hours - 24 Hrs || 130 Hrs
Sawing machine hours - 126 Hrs || n/a
Factory Overhead allocation for Washington County Courthouse Project =
$485 divided by 126 hrs = $3.85 Per Sawing Machine hour (Sawing department)
$1,790 divided by 130 hrs = $13.77 Per Direct Labour hour (Polishing department)
Bid Price of the Project = $35 Per Square Meter.
Actual dimensions is 4 by 25 Square meter
Actual Revenue therefore = 4 x 25 x 35 = $3,500
Actual Costs = Sawing ($7.29 x 126 hrs) + Polishing ($16.50 x 130 hrs) = ($918.54 + $2,145) = $3,063.54