Answer:
$50.57 ; $175,573.6
Explanation:
The computation of the fixed and variable portions of overhead costs based on machine-hours using high low method is shown below:
Variable cost per hour = (High Overhead cost - low overhead cost) ÷ (High machine hours - low service hours)
= ($581,145 - $503,775) ÷ (8,020 hours - 6,490 hours)
= $77,370 ÷ 1,530 hours
= $50.57
Now the fixed cost equal to
= High overhead cost - (High machine hours × Variable cost per hour)
= $581,145 - (8,020 hours × $50.57)
= $581,145 - $405,571.4
= $175,573.60