Step-by-step explanation:
Let us assume if they work together, the work is completed in t hours.
So, the work completed by both workers in 1 hour = [tex](\frac{1}{t} )[/tex]
The amount of time taken by Gab to finish 1/ 7 of job = 3 hours
So, the amount of time taken to finish the job = 3 x 7 = 21 hours
So, the fraction of job completed by gab in 1 hour = [tex](\frac{1}{21} )[/tex] ... (1)
The amount of time taken by Torres to finish 1/ 10 of job = (3 + 1.5) hours
So, the amount of time taken to finish the job = 4.5 x 10 = 45 hours
So, the fraction of job completed by Torres in 1 hour = [tex](\frac{1}{45} )[/tex]
So, the amount of work completed by Gab and Torres in 1 hour = [tex](\frac{1}{21} ) + (\frac{1}{45} )[/tex]
[tex]\implies \frac{1}{21} + \frac{1}{45} = \frac{1}{t} \\\implies \frac{45+ 21}{21 \times 45} = \frac{1}{t}\\\implies \frac{66}{945} = \frac{1}{t}\\\implies t = \frac{945}{66}= 14.3[/tex]
Hence, it would take 14.3 hours to complete the work together.