Gourmet Pretzels bakes soft pretzels on an assembly line. It currently bakes 800 pretzels each 8-hour shift. If the production is increased to 1,200 pretzels each shift, then productivity will have increased by:___________.
A. 50%
B. 33%
C. 25%