Answer: True
Explanation: Gantt charts are normally built by applying an early start time strategy, where every work is organized to start shortly after the requirements are finished. This increases the quantity of time that a task can be delayed without resulting in a delay to the following tasks and the total work finished date. However, it records the works to be conducted on the vertical line and time on the horizontal line.