The _________shows all the individuals associated with each work item in the work breakdown structure, as well as all the work items associated with each individual.

A: project scope document
B: work breakdown structure
C: responsibility assignment matrix
D: network diagram

Respuesta :

Answer:

C: responsibility assignment matrix

Explanation:

Responsibility assignment matrix is also called Linear responsibility chat, or RACI, this acronym stands for Responsible, Accountable, Consulted and Informed. This explains the role of various participants in completing a task or delivering on a particular project.

Responsibility assignment matrix helps to assign definite roles to every individual or department involved in a project.