Scope Change Control is primarily concerned with: a. Influencing the factors that create scope changes. b. Defining a baseline for performance measurement and control. c. Developing a written scope statement which will serve as the basis for future project decisions. d. Assigning work elements to the proper organizations.

Respuesta :

Answer:

A - Influencing the factors that create scope changes.

Explanation:

Scope Change Control is process of project management that ensure the possible changes that may occur during the process of the project execution is well managed in such a way that such changes do not affect the outcome or success of the project. There is no doubt that scope change is inevitable in project , and so many factors could lead to change in the course of project execution, so this concept entails change management during project execution.