Start-to-start (SS)
Explanation:
Start-to-start (SS) is a term of logical relationship which means that for a particular project to start, another project that is related with it must have also started and be in progress. For example, for the editing of a book to take place, the writing of the book must have started.
It means activity A must begin else activity B will not start.
Answer:
The correct answer is letter "C": Finish-To-Finish (FF)
Explanation:
The Precedence Diagramming Method (PDM) is useful for keeping an agenda of the necessary activities of a project. The PDM establishes there are four (4) types of relationships linking those activities: Finish-To-Start (FS), Start-To-Start (SS), Finish-To-Finish (FF), and Start-To-Finish (SF).
The Finish-To-Finish (FF) relationship describes how activities can start at different times, thus, they will last different times but are scheduled to finish together.