Respuesta :
Answer: $1150
Explanation:
It is give that SPI and CPI is equal to 1, which means project will continue to spend at the same current rate. Therefore we can use following formula:
EAC = BAC/CPI
BAC = Budget at completion = $1150
EAC = $1150/ 1 = $1150
Answer: The answer is $1,150
Explanation:
Using the formula EAC = BAC/ CPI
Where EAC = Estimate at completion , BAC = Budget at completion, CPI = Cost Performance Index,
Since the project will continue to spend money at the same rate
Since the original project budget is $1,150 then,
EAC = 1,150 / 1
= 1,150
Therefore the estimate at completion is $1,150