Answer:
Detailed answer for the question :
"The network and associated requirements for systems analysts and programmers for the GUMBY project are as follows: a. Draw the network. Compute ESs, LSs, and total slack times.b. Then show the separate resource loadings for systems analysts and programmers, assuming ESs.c. Suppose the maximum weekly availability is eight systems analysts and five programmers. Can activities be scheduled to satisfy these constraints without delaying the project"
Explanation:
Consider page one of attachment only.