Answer:
B
Explanation:
Given Time (T) = 4
Standard deviation of daily demands (STDdaily) = 10
Standard deviation of usage = STDdaily × sqrt T
= 10 × 2
=20
Based on the information given the standard deviation of usage during lead time is B) 20.
Using this formula
Standard deviation=√Variances of lead time number of days of lead time
Let plug in the formula
Standard deviation=√4 days(10x10)
Standard deviation=√4 days(20)
Standard deviation= √400
Standard deviation=20
Inconclusion the standard deviation of usage during lead time is B) 20.
Learn more about standard deviation here:https://brainly.com/question/475676