Answer:
The probability of completing the project under 35 days is 0.1587.
Step-by-step explanation:
Let X = completion date of the time needed to complete the project.
The expected date is, E (X) = 40 days.
The standard deviation of the date is, SD (X) = √(5 + 4 + 6 + 4 + 6) = 5 days.
Compute the z-score for X = 35 as follows:
[tex]z=\frac{X-E(X)}{SD(X)} =\frac{35-40}{5}=-1[/tex]
The probability of completing the project under 35 days is:
[tex]P(X<35)=P(Z<-1)\\=1-P(Z<1)\\=1-0.8413\\=0.1587[/tex]
Thus, the probability of completing the project under 35 days is 0.1587.